BRIEF CONTOUR OF SUJALAM SUFALAM YOJNA
(1) Schemes for Mehsana, Patan, Gandhinagar,
Banaskantha, Sabarkantha and Ahmedabad district.
- Sujalam Sufalam Yojana having length of 280 k.m. from Kadana
dam to Banas river, will be prepared, wherein 700 million cubic
meter flood water will be flown. Which now flows in the ocean. By
this scheme to be undertaken at the cost of Rs. 460 crore, 21 dry
river and hundreds of ponds will be revived.
- Main nine reservoirs including Dharoi, Mazum, Meshwo, Vatrak,
Hathmati, Goohai, Mukteshwar, Sipu and Dantiwada which are filled
upto 50% capacity will be filled at 100% capacity by one million
acre feet narmada water from Narmada Main Canal out of Gujarat’s
share in the Narmada Project and extention work of its canals will
be undertaken and checkdams will be constructed barring irrigated
areas. Besides 5000 village ponds of these areas will be filled by
Narmada water. Estimated cost of this scheme is Rs. 2969 crore.

- Work of Distribution canal linking Sujalam Sufalam canal from
Narmada Main Canal will be taken up at the cost of Rs. 73 crore,
out of which approximately 4 lakh hectaree agriculture land will
get benefit of irrigation.
- It is planned to lay bulk and distribution lines at the cost
of Rs. 923 crore for potable water in these six districts. There
is a provision of Rs 4425 crore for these six districts.
(2) Scheme for Panchmahal and Dahod district.
In the tribal areas of Panchmahal and Dahod
districts, irrigation facility will be extended by the scheme of
Kadana left coast high level and Panam reservoir high level scheme.
Water conservation will be increased by constructing check dams and
deepening ponds. For this purpose cost of Rs. 382 crore has been
estimated. It will cost Rs. 410 crore for potable water in these
districts. Thus Provision of Rs. 792 has been made for these two
districts.
(3) Scheme for Kutch district
In Kutch District work of 1000 check dams, 15 tidal regulators,
33 dams, 19 recharge ponds, 150 recharge well be undertaken at the
cost of Rs. 272 crore and the work of transmission and distribution
water supply network at the cost of Rs.220 crore. In all expenditure
of Rs. 492 crore has been planned.
(4) Scheme for Surendranagar district.
In Order to revive the dry land of dry underground of
Surendranagar district, Rs. 85 crore will be expended and new and
big 107 check dams will be constructed in 17 rivers and they will be
revived permanently. Besides, 27 reservoirs of small and medium
irrigation will also be filled. Pipeline project for potable water
at the cost of Rs. 244 crore will also be taken up. In all,
expenditure of Rs. 329 crore has been planned. |